ENESSERE Hercules Wind Generator is not covered by the binding legislation of mini wind turbines both for the installed power and the dimensions, since standing under 15 meters of height, there are no constraints with regard to the landscape national laws and moreover, the installed power is less than 60kW. But every time you plan to install a turbine, you must consult the municipality to make sure that there no regional or municipal law which impose other rules. In most cases (almost all) there is an obligation to submit a DIA/SCIA with the construction start date. Tacit consent applies, that is after 30 days from the submission date, if there are no objections on behalf of the municipality, work can commence. If the unit will be connected to the network grid, the famous energy bill will be required, and a GSE application will be required.